AI Data Center Power Crisis: 125 GW Is Projected for 2030, but Only 95 GW Is Running or Approved

The AI data center power crisis rests on one projection: ETDatacenters’ report on the scramble for data center power projects US data center electricity demand of 125 GW by 2030, up from 35 GW in 2024. The same report counts 53 GW of US data center load as operating and another 42 GW as approved or under construction, so 95 GW is running or in the pipeline and about 30 GW of the 125 GW is not. The supply the report names for projects above 1 GW, gas turbines, is sold out through 2029 at GE Vernova, Mitsubishi Power and Siemens Energy, with orders extending to 2031.

Google · Preferred Sources

Don't miss new tech stories on Google

Add Tech Insider once in the Google app and our stories appear in your news suggestions.

Add Now

Where the power crisis starts: 53 GW running, 42 GW approved, about 30 GW unbacked

ETDatacenters reports that operational US data center load has risen from 23 GW in 2023 to 53 GW, with another 42 GW approved or under construction. Together that is 95 GW, and the distance from there to the 125 GW projection is 30 GW. About 76 percent of the 2030 figure is therefore running or in the pipeline, and the remaining 24 percent is the part the report’s own counts do not cover. Put the other way, the build still needed by 2030 is 72 GW (125 minus 53), not 125 GW. The source describes the first two numbers as load and the 125 GW as demand, so this comparison assumes they are comparable.

Approved projects can slip, and our report on delayed and canceled AI data centers follows the approved projects that slip.

Forecasts in this field also move quickly. ETDatacenters notes that grid planners’ ten-year forecasts of added demand climbed sevenfold, from 24 GW in 2022 to 166 GW by 2025. That is a different series from the 125 GW, but it shows the same pattern: a projection that rises sevenfold in three years is better read as a line of requests than as a measurement.

Shares of the national total depend on the method. One 2026 analysis cited by C2ES puts data centers at 9 to 17 percent of US electricity generation by 2030, and C2ES cites an estimate that AI workloads account for up to 25 percent of data center electricity demand. Globally, the IEA’s executive summary on energy and AI has data-centre demand growing 17 percent in 2025 to 485 TWh and roughly doubling to 950 TWh in 2030, around 3 percent of global electricity demand. Earlier coverage, including the agency’s news release, cites 945 TWh for the same projection; this article uses 950 TWh throughout.

The energy figures also give a check on the units. Spread over 8,760 hours in a year, the IEA’s 950 TWh for the whole world in 2030 is an average draw of about 108 GW, less than the 125 GW projected for the US alone. The two figures come from different publishers, so the comparison is implied, not published, but it suggests 125 GW is better read as provisioned capacity or peak demand than as the power the sites will draw on average.

Why a gigawatt campus strains a grid built around 30 MW data centers

An arXiv study of AI data center power says traditional data centers have typically run below 30 MW in total, while AI facilities can reach hundreds of megawatts or gigawatt levels, with racks above 100 kW. The Open Compute Project’s account of the same shift puts a single high-end GPU at 1,000 to 1,200 W, and rack power at about 40 kW for an H100-class rack, about 120 kW for a Blackwell GB200 rack and a projected 600 kW to 1 MW for Rubin-generation racks by 2027. Against the H100 rack that is 3 times the power, then 15 to 25 times.

The load also behaves differently. Open Compute says that as tens of thousands of GPUs synchronize, checkpoint and fall idle together, the load can rise or collapse by a large fraction in seconds.

Airsys defines Power Compute Effectiveness (PCE) as provisioned power for compute divided by provisioned total data center power. In its illustrative 20 MW colocation facility, 5.9 MW goes to infrastructure before reaching IT, a PCE of 0.705. If that ratio held nationally, 125 GW of provisioned power would deliver about 88 GW to compute; that is our illustration of the example, not a measurement.

Before signing for colocation or powered-shell capacity, these are the questions worth putting to the host:

  • The host’s PCE, or the split between provisioned and compute power at your delivery date.
  • Contracted megawatts against energised megawatts, with the date each tranche is energised.
  • Rack density at delivery, and the density the electrical design is rated for.
  • How the site behaves on load steps, and whether the utility has set any ride-through or curtailment terms.

What can be named: Crane due in 2028, Kilby signed, turbines booked to 2029

Two named projects can be sized against the projection. On 22 June 2026 Chevron announced that it had signed an agreement with Microsoft to develop a co-located power facility in West Texas that will supply a Microsoft data center “under a 20-year power purchase agreement”. The project, Kilby, is about 2.67 GW, and Chevron’s page, read on 13 November 2026, shows it as signed rather than under negotiation. The second is the Crane Clean Energy Center, the restarted Three Mile Island Unit 1, about 835 MW under a 20-year Microsoft agreement. Constellation’s announcement, read on 13 November 2026, says “The CCEC is expected to be online in 2028.” C2ES gives 2027 for the same unit; the owner’s own page carries the later date, so 2028 is used here. Together the two come to about 3.5 GW, or 2.8 percent of 125 GW.

Project or route Size Date Status Source
Crane Clean Energy Center (Three Mile Island Unit 1 restart) About 835 MW Expected online 2028 (page read 13 November 2026) 20-year Microsoft agreement Constellation
Project Kilby, Chevron and Microsoft, West Texas About 2.67 GW Announced 22 June 2026 Signed 20-year power purchase agreement, co-located supply Chevron newsroom
Gas turbines from GE Vernova, Mitsubishi Power and Siemens Energy Preferred for projects above 1 GW Sold out through 2029, orders to 2031 Backlog ETDatacenters
New natural gas plant projects $228 billion Under way IIR estimate of projects meeting AI demand ETDatacenters

Gas is where the bulk of new supply has to come from. ETDatacenters says GE Vernova, Mitsubishi Power and Siemens Energy are sold out through 2029, with orders extending to 2031, and that turbines are preferred for projects above 1 GW. IIR estimates that $228 billion of new gas plant projects are under way, and C2ES says unabated natural gas, followed by intermittent renewables, remains the dominant source of electricity for US data centers. With the order book running to 2031, turbines ordered after this report look unlikely to be energised before 2030 ends, which makes it hard to see them serving the unbacked 30 GW inside the window. That is an inference from the backlog dates, not a delivery schedule from the manufacturers.

Bank of America’s analysts, as reported by Energy Reader, project that the US will need more than 230 GW of new generating capacity over five years while regulated utilities add only about 93 GW of accredited supply, a gap of 137 GW on those figures.

Texas has paused about 200 GW of requests, more than the national forecast

Siting resistance can be read as a measurement of the queue. ETDatacenters records over 500 data center moratoria across 42 US states. New York has temporarily banned new data centers above 50 MW, and Texas has paused new grid interconnections for approximately 200 GW of requests. That is 1.6 times the 125 GW national projection. If those requests are mostly data center load, they exceed what the forecast expects to be built, which would make the pause a queue-management step more than a ceiling on demand.

ETDatacenters reports that Microsoft, Meta, Amazon and Google’s combined data center spending is projected to exceed $700 billion in 2026, up from $64 billion in 2018, about 11 times. For the grid side of this, see our pages on FERC’s order on AI data center power and the utility grid overhaul.

Planning to 2030: treat 95 GW as the backed figure and buy power by delivery date

The figures that carry weight in a capacity plan are the 53 GW operating and the 42 GW in the pipeline, 95 GW in all. The 125 GW is a request line: its last 30 GW is the part the report’s operating and pipeline counts do not cover, and turbines are sold out through 2029. In our assessment, a plan built on 95 GW, with the remaining 30 GW treated as upside, fits the evidence better than one built on the headline. The 125 GW already includes the 53 GW that is running, so the two should not be added.

Capacity bought with an energisation date and a clause that bites if the date slips is worth more than capacity sold on headline megawatts. Named supply of the Crane and Kilby type is real but small, about 3.5 GW across both. Sites in New York above 50 MW, or in Texas where interconnections are paused, deserve a written answer from the host on queue position before a commitment is signed.

Marcus Chen

Marcus Chen

PC hardware, storage and engineering

Marcus Chen covers PC hardware, storage and engineering for Tech Insider: processors, graphics cards, SSDs and hard drives, home servers and backup, and the engineering choices behind them. He builds comparisons from manufacturers' specifications, published independent test results and Tech Insider's own calculations, and writes plainly about what the evidence supports.