Starship’s First Florida Launch Is Listed for Dec. 10, but the FAA Says SpaceX Must Obtain a Licence

SpaceX Stats lists Starlink Group 30-1, which would be the first Starship launch from LC-39A and from Florida, as no earlier than Dec. 10, 2026. The date belongs to that tracker: Space Launch Schedule’s program-status page targets the first Florida flight for late 2026 or early 2027 and says SpaceX still needs a flight license for LC-39A. The FAA’s environmental approval for the pad is a different step from that licence: the FAA’s Starship page for Kennedy says SpaceX must obtain a vehicle operator license for Starship-Super Heavy launch and landing operations.

Google · Preferred Sources

Don't miss new tech stories on Google

Add Tech Insider once in the Google app and our stories appear in your news suggestions.

Add Now

The Dec. 10 entry: one mission, two first-flight vehicles, no recovery plan

On its launch page for the mission, read on Nov. 12, 2026, SpaceX Stats names the flight Starlink Group 30-1, flown on a Starship V3 from LC-39A at Kennedy Space Center. It calls the launch the first Starship launch from historic LC-39A and the first from Florida. The vehicles listed are booster B23 and ship S43, each on its first flight, and the payload is Starlink V3 satellites bound for low Earth orbit, with SpaceX as the customer.

The same page also says booster assignments and recovery methods are unknown, so the B23 and S43 names read as listings rather than a settled manifest. NextSpaceflight’s hardware record for Ship 43 lists a first cryogenic proof test at the Cryostation, Massey Outpost, Texas on Oct. 23, 2026, and says the ship conducted a pair of such tests within the same window to verify the structural integrity of the vehicle. “NET” means no earlier than: it sets a floor for the launch, not a day SpaceX has committed to.

Two trackers disagree: a Dec. 10 floor against a late 2026 or early 2027 window

Space Launch Schedule’s program-status page says the FAA granted environmental approval for Starship operations at LC-39A, up to 44 launches per year, though SpaceX still needs a flight license, and it targets the first Florida Starship flight for late 2026 or early 2027. SpaceX’s own Starship V3 update gives the earliest date in the set, late 2025, and that date had passed by Nov. 12, 2026. Dec. 10 therefore looks like the earliest the launch could happen rather than the likeliest day, because Space Launch Schedule’s page says SpaceX still needs a flight license.

SourceDate or window it givesWhat has to be true for it to hold
SpaceX StatsStarlink Group 30-1 no earlier than Dec. 10, 2026A flight licence, a ready pad and the Starbase flight before it out of the way
Space Launch ScheduleFirst Florida flight targeted late 2026 or early 2027SpaceX still needs a flight license for LC-39A
SpaceX’s Starship V3 updateFirst Florida launch from LC-39A in late 2025, pending environmental reviewsNot applicable: the late 2025 date had passed by Nov. 12, 2026

The environmental approval is a separate step from the flight licence

The FAA’s page for Starship at Kennedy says the final environmental impact statement analyses up to 44 Starship-Super Heavy launches a year and up to 44 Super Heavy landings a year, with landings at LC-39A, on a droneship or as expendable ocean landings. A TCPalm article reports that the FAA approved Starship launch operations from LC-39A in early 2026.

None of that is a licence. The FAA states on the same page: “The successful completion of the environmental review process does not guarantee that the FAA would issue a new or modification of an existing vehicle operator license.” It also says SpaceX “must obtain a new or modification of an existing vehicle operator license from the FAA for Starship-Super Heavy launch and landing operations.” A launch date that depends on the licence therefore depends on a decision that Space Launch Schedule’s page says SpaceX still needs, which is how a date can look settled in a listing while the launch is not.

Flight 15’s listed date is 46 days after Flight 14 and 27 days before Dec. 10

SpaceX’s Flight 14 page says that on Monday, Sept. 28, 2026 at 7:48 a.m. CT (8:48 a.m. EDT), Starship lifted off from Starbase, Texas on its 14th flight and first attempt to go to orbit, and it describes the flight as the first orbital Starship flight, carrying 26 Starlink V3 satellites. Space Launch Schedule says all 2026 flights, three launches, flew from Pad 2 at Starbase while Pad 1 is being rebuilt, so every Starship flight it counts this year started in Texas.

SpaceX Stats lists Flight 15, Starlink Group 31-2, for Friday Nov. 13, 2026 at 22:45 UTC from Pad 2 at Starbase. SpaceX’s Flight 15 page says the flight is preparing to launch as soon as Friday, Nov. 13, pending regulatory approval, and Space Launch Schedule’s Starship page also projects Flight 15 for November 2026, with a note that the date and time may change (checked Nov. 12, 2026). Counted from the listed dates, Flight 14 to Flight 15 is 46 days (Sept. 28 to Nov. 13), and Flight 15 to the Florida debut would be 27 days (Nov. 13 to Dec. 10). Flight 15 is a listed date, not a completed flight, so the 46 is itself provisional.

The two intervals are not like for like, because the Florida flight uses a different pad and new vehicles. Both point the same way, though: Dec. 10 leaves little room for a Flight 15 delay, or for anything Flight 15 teaches SpaceX that needs fixing before the next stack flies. Our Flight 15 double-catch report and our earlier report on Flight 15 and the Florida pad cover that flight itself.

From “late 2025” to NET Dec. 10: how the Florida target has moved

SpaceX’s own Starship V3 update says: “Pending completion of environmental reviews, SpaceX intends to conduct Starship’s first Florida launch from LC-39A in late 2025.” That target passed without a Florida launch. As of Nov. 12, 2026 no Starship launch from Florida has taken place: SpaceX’s page lists Starship Flight 15 from Starbase as its upcoming launch, while SpaceX Stats puts the Florida attempt at no earlier than Dec. 10 and Space Launch Schedule targets late 2026 or early 2027.

Two Florida pads are in the Starship paperwork, and only one is in this listing

SLC-37 at Cape Canaveral is the second Florida pad in the approvals process. TCPalm reports that SpaceX holds Air Force approval to redevelop Space Launch Complex 37, and the FAA’s page records a supplemental environmental review for it.

PadApproval statusAnnual figuresRole here
LC-39A, Kennedy Space CenterFAA final EIS done; TCPalm reports operations approved in early 2026; flight license still needed per Space Launch ScheduleUp to 44 launches and 44 Super Heavy landingsSite of the Starlink Group 30-1 listing; HLS LEO Demo for NASA’s Artemis program targeted for June 2027 from LC-39A, with the date not yet set
SLC-37, Cape Canaveral Space Force StationAir Force approval to redevelop; FAA notice of intent for a supplemental EIS on Sept. 29, 2026; comment period ended Oct. 14, 2026Up to 76 launches and 152 landings (76 booster, 76 ship)Second Florida pad in the Starship approvals process

WESH reports that SpaceX is asking for those 76 launches and 152 landings a year at SLC-37. The stakes for Starlink are set by size, in Space Launch Schedule’s telling: it says the V3 satellites “are too large to launch on Falcon 9” and describes Starship as the only vehicle that can build out SpaceX’s planned constellation.

The Florida figures are modest next to the scale the FAA describes elsewhere. The FAA’s Starship page says Phase 2 would include up to 456 launches and 912 annual landings (456 of Starship and 456 of Super Heavy), and our report on the 456-launch request covers that filing.

Dec. 10 holds only if three things line up

Our assessment: Dec. 10 is a plausible floor, and it holds only if Flight 15 flies on its listed date with a result that does not force changes, the FAA issues the flight licence, and a pad that has not yet launched a Starship is ready for its first B23 and S43 flight. Of the three, the licence is the one outsiders can see least, and the tracker window of late 2026 or early 2027 allows for it to run past December. The missed “late 2025” target also shows that a Florida date can move before the launch happens.

For anyone with money or leave at stake, book refundable travel and lodging only, and treat any plan built on Dec. 10 as provisional until a licence is reported. The FAA’s Starship Kennedy page, SpaceX’s own Starship updates and the SpaceX Stats listing are the places to check for changes, and the date may well move.